On paper Europe has enough announced e-SAF. With realistic delays, almost none of it arrives by 2030.
e-SAF market map, draft v0.3, 26 Nov 2026. Sources: Transport & Environment (project list, May 2025), company and press pages (status check, Nov 2026), Eurostat 2024 jet fuel, public CO2 data.
Where things stand
Circle size shows capacity. Click a legend item to show or hide that layer. Hover (or tap) a marker for details. Balkans: no e-SAF project found, but large refineries there already invest in hydrogen and bio-SAF (INA Rijeka, OMV Petrom, Motor Oil Corinth). Italy has no project in our list. Both may be data gaps.
Ukraine: no e-SAF, PtL or Fischer-Tropsch project found (medium confidence; official Ukrainian sources not read directly). Only a 2 MW hydrogen pilot is contracted; the other hydrogen plans (Zakarpattia, Reni, Lviv, Odesa) are concepts without financing. Kremenchuk, the largest refinery, has been hit repeatedly and was reported halted in 2026; Odesa is idle. Civil airspace has been closed since February 2022, so there is no domestic jet demand, and ReFuelEU does not apply. Biogenic CO2 exists (7 biomethane plants, about 111 mcm/yr; bioethanol capacity about 1 Mt) but no CO2 volumes are published. Shown as a long-term option that would depend on peace, airspace reopening, grid recovery and war-risk cover, not as an active project.
Required vs delivered: three scenarios
EU27 only; Norway, Iceland, UK and Switzerland are in the table below. Scenarios use our assumptions, not data: base = construction 90%, FEED 30%, announced 8% reach operation, with delays of 1, 2 and 3 years and a 50/80/100% ramp-up; cautious = 80/15/3% and delays of 2, 3 and 4 years.
2030
2032
2035
By region
kt of e-kerosene per year. Jet fuel use is Eurostat 2024. The quota is EU-wide, so the regional requirement is our pro-rata allocation (share of jet fuel use), not law; fuel can be shipped between regions. Supply shown for 2032 in three scenarios, and the base case for 2035. All e-SAF figures already exclude the bio share of hybrid projects.
| Region | Jet fuel use | Need 2030 | Need 2032 | Need 2035 | 2032 announced | 2032 base | 2032 cautious | 2035 base |
|---|---|---|---|---|---|---|---|---|
| NW Europe | 21,769 | 261 | 435 | 1,088 | 994 | 101 | 13 | 251 |
| Iberia | 9,184 | 110 | 184 | 459 | 397 | 4 | 1 | 33 |
| Italy | 4,909 | 59 | 98 | 245 | 0 | 0 | 0 | 0 |
| Central Europe | 3,125 | 38 | 62 | 156 | 48 | 0 | 0 | 4 |
| Nordics and Baltics | 2,578 | 31 | 52 | 129 | 613 | 64 | 7 | 151 |
| Balkans | 2,604 | 27 | 45 | 112 | 0 | 0 | 0 | 0 |
| Associated | 14,958 | - | no EU quota | - | 279 | 4 | 0 | 22 |
| Other EU | 1,529 | 18 | 31 | 76 | 0 | 0 | 0 | 0 |
Ten candidate sites, adjusted for competition and CO2
Score out of 20 (refinery, airport and pipeline, CO2, power). The CO2 part is now based on documented sources (below), and the total is reduced for competing e-SAF projects within 150 km (-1 for 50 kt or more, -2 for 250 kt or a developer already on site) and where the owner pursues its own SAF route (-1).
| # | Site | Adj. score | Competition | Airport and pipeline |
|---|---|---|---|---|
| 1 | Schwechat (Vienna), AT | 17 (was 18) | OMV already runs its own SAF and hydrogen plans | Airport pipeline confirmed; OMV builds electrolysers. |
| 2 | Grangemouth, UK | 16 (was 15) | no e-SAF competitor found within 150 km | Refinery closed 2025; open site; project stalled. |
| 3 | Schwedt, DE | 13 (was 16) | e-SAF developer on site, 68 kt within 150 km | Enertrag project, EUR 350M grant; crude supply risk. |
| 4 | Grandpuits, FR | 13 (was 15) | TotalEnergies builds bio-SAF here | Owner builds bio-SAF; pipeline unverified. |
| 5 | Wesseling / Cologne, DE | 13 (was 14) | no e-SAF competitor found within 150 km | Airport link and pipeline not yet checked |
| 6 | Tarragona, ES | 12 (was 15) | Repsol is going the methanol route | No jet pipeline found; methanol route. |
| 7 | Sines, PT | 12 (was 15) | 155 kt e-SAF within 150 km | Airport link and pipeline not yet checked |
| 8 | Heide, DE | 12 (was 14) | no e-SAF competitor found within 150 km | Airport link and pipeline not yet checked |
| 9 | Litvinov, CZ | 12 (was 14) | no e-SAF competitor found within 150 km | Airport link and pipeline not yet checked |
| 10 | Rotterdam (Pernis/Evos), NL | 10 (was 14) | e-SAF developer on site, 285 kt within 150 km | Airport link and pipeline not yet checked |
CO2: what we could document
Plant need: 7-8 kt e-SAF per year needs about 25-30 kt CO2; 60-70 kt e-SAF needs about 200-250 kt CO2. Figures are from company reports, an open database (CRONUS) and one university model; no registry data was available, and "none documented" means not found, not absent.
| Site | Documented biogenic CO2 within 100 km | Small plant (25-30 kt) | Large plant (200-250 kt) | Main sources and caveats |
|---|---|---|---|---|
| Schwechat (Vienna) | ~690 kt (about 490 stated) | Yes | Yes, if one large source is secured | Pischelsdorf ethanol 188, Vienna waste plants ~313 (mixed), Simmering biomass ~190 (derived). Also claimed by Austrian CCS plans. |
| Grangemouth | ~1,311 kt (modelled, 12 sources within 75 km) | Yes | Yes (about 5x) | Markinch biomass 431, Norbord Cowie 180, distillery fermentation ~141. University of Edinburgh model 2023. |
| Schwedt | ~150 kt | Yes | Unlikely | Verbio Schwedt 95, Berlin biomass CHP 54. LEIPA is already contracted to the funded Enertrag project. |
| Grandpuits | 185 kt at 88 km | Likely | Unknown | Arcis-sur-Aube sugar/ethanol 185. Paris waste plants: biogenic share not published. Own CO2 is fossil. |
| Wesseling / Cologne | none documented | Unknown | Unknown | RWE sewage-sludge plant and Cologne waste plant named, no figures. |
| Tarragona | none documented | Unknown | Unknown | Cement (Molins ~1 Mt, mostly fossil) tied to storage plans. |
| Sines | none documented | Unknown | Unknown | Navigator Setubal pulp mill (61 km): no biogenic figure. Navigator e-fuel JV is at Figueira da Foz, 290 km away. |
| Heide | none documented | Unknown | Unknown | Holcim Laegerdorf 1.0-1.2 Mt planned, mostly fossil process CO2. |
| Litvinov | none documented | Unknown | Unknown | Only the Unipetrol site itself (fossil, ~650 kt). |
| Rotterdam (Pernis/Evos) | none documented | Unknown | Unknown | AVR Rozenburg 482 kt planned capture, mixed waste, earmarked for storage or greenhouses. |